Windows installed 90% & Mock-Up Siding

Tamarack and TruFrame started installing the Sierra Pacific Windows (doors next week). Appreciate the delivery of both, a quality window, on time and within our budget! Correction, before our scheduled time. Thank you Ken Matoon and the Sierra Pacific team!

Living room facing East

IMG_0599

The living room windows facing East toward Ken’s Artisan Bakery. Full height floor to ceiling.

IMG_0605

The dining room is a wall of windows from inside looking out towards Pine Street.

IMG_0598

An example of the stair way looking up to the light coming at the top. WORKS designed these windows to open to provide a nice draft of air flow.

IMG_0601

The LVL screen wall being installed that the perforated steel stair case will sit nestled in between (see last months post for the sneak peak).

IMG_0606

An mock-up of the corten steel perforated cladding and the corner detail that WORKS provided.

Published by Ryan Zygar in tandemDUO on December 17, 2009 at 7:46 am. Leave a comment »

Mocked up the stair system at the tandemDUO

TandemDuo Stairs TandemDuo Stairs TandemDuo Stairs

Published by Ericka Carlsen in tandemDUO on November 10, 2009 at 11:49 pm. Leave a comment »

truframe placed the living room wall today on the tandem

The tandemDUO is moving along well. It was decided to hold on ordering windows until the walls fell went to the respective locations. This building is beautiful, cannot wait to see the kitchen lid installed. Truframe and Tamarack installed the steel posts today as well.

The Living Room

The Living Room

Setting posts.

Framing2 10-15-09Framing 10-15-09

Published by Ryan Zygar in tandemDUO on October 15, 2009 at 9:57 am. Leave a comment »

Steel has been installed and Kitchen decking is being instaled at TandemDUO

TandemDuo Steel & Decking

Published by Ericka Carlsen in tandemDUO on October 14, 2009 at 12:43 am. Leave a comment »

Framing with TruFrame

We are excited to have TruFrame apart of this project. The quality is going to begin to show as this building comes together! The first floor walls and some of the steel supports were installed at the TandemDUO today!

Framing with TruFrame

Framing with TruFrame

Published by Ericka Carlsen in tandemDUO on October 2, 2009 at 2:47 am. Leave a comment »